USA: Court overturns BLM approval of 104MW Echanis

Thu Apr 20 2017, 20:45 PM

Columbia Energy Partners' project is planned for a site in Oregon

A federal court has overturned the Bureau of Land Management's (BLM) approval of Columbia Energy Partners’ 104MW Echanis project in Oregon. The US District Court described the BLM’s approval "ill-informed," because of the project's likely impact on the winter habitat of the sage grouse.

 